FERC Involvement In Southern’s Cypress Pipeline Project
The Federal Energy Regulatory Commission (FERC) is the lead federal
agency responsible for authorizing the Cypress Pipeline Project
under the National Environmental Policy Act (NEPA). On January
5, 2005, the FERC assigned pre-filing Docket No. PF05-7-000 to
the Cypress Pipeline Project. Interested parties who wish to correspond
with FERC about this project should refer to this docket number.
Southern Natural Gas has received permission from FERC to participate
in the NEPA pre-filing process which is intended to identify and
address project issues as early as possible in the planning and
approval effort. Comments provided to the FERC under this process
will be addressed by the FERC in its project evaluation.
The FERC plans to prepare an Environmental Impact Statement (EIS)
for its project evaluation. As part of the EIS process, FREC will
host a series of meetings designed to provide an opportunity for
public review and comment about the project. Additional information
about the FERC and the NEPA environmental review process can be
obtained through the FERC Web site at:
http://www.ferc.gov/for-citizens/get-involved/process.asp
|